The 60-Day Clock: FERC Just Forced Six Grid Operators to Rewrite the Rules for Every Data Center Over 20 MW

FERC's June 18 show-cause orders don't pick grid versus behind-the-meter. They accelerate both at once.

Christopher Johnson's avatar
Christopher Johnson
Jul 21, 2026
∙ Paid
Aerial view of a hyperscale data center campus at dusk showing both high-voltage transmission substation infrastructure on the left and an on-site natural gas turbine power plant on the right, representing the two pathways, grid connection and on-site generation, that FERC's June 18 orders put on the clock at once.
FERC's June 18 show-cause orders reset the rules for how every data center above 20 MW connects to the U.S. interstate transmission system, and put both infrastructure pathways on a 60-day clock at the same time.

$163 billion. That is the cumulative cost PJM ratepayers face from 2028 through 2033 if the current interconnection system continues unchanged — roughly $70 per month added to the average household utility bill by 2028, according to the NRDC.²⁹ It is the downstream consequence of a simple, broken process: data centers need power, the grid cannot connect them fast enough, and the cost of that failure lands on everyone except the operators causing it.

On October 23, 2025, DOE Secretary Chris Wright invoked Section 403 of the DOE Organization Act, a rarely-used statutory tool that compels FERC to act, and directed the commission to fix data center interconnection. FERC issued its Order Regarding Intent to Act on April 16, 2026.² Then, on June 18, 2026, it delivered: tailored show-cause orders under Section 206 of the Federal Power Act to all six regional grid operators it oversees, directing each to either justify why its current large-load tariffs remain just and reasonable or file changes that fix them.³² The proceeding that determines how every data center above 20 MW connects to the U.S. interstate transmission system is now live, and it has a clock attached.

Energy Industry Insights from Avanza Energy is a reader-supported publication. To receive new posts and support my work, consider becoming a free or paid subscriber.

FERC did not pick a winner. It did something the market had not priced: instead of one national rule litigated for two years, it gave each grid operator 60 days to defend or rewrite its large-load tariffs, and teed up five specific reforms spanning cost allocation, co-location, and flexible load.³³ The instrument is faster than a rulemaking and more surgical than a policy statement. The consequence most analysts will miss: it accelerates grid-connected and behind-the-meter data center strategies at the same time. Both bets just became more investable, not one at the other's expense.

The scale of what is at stake

U.S. data center power demand reached 61.8 GW in 2025, a 22% year-over-year increase, and S&P Global projects it rising to 134.4 GW by 2030.¹¹ That trajectory requires connecting hundreds of new facilities to a transmission system whose interconnection queue now holds more than 2,060 GW of backlog and averages nearly five years of wait time, up from under two years in 2008.⁷ Of all projects requesting interconnection between 2000 and 2019, only 19% reached commercial operation by the end of 2024.⁷

Moody's projects $3 trillion in global data center infrastructure investment through 2030.²⁸ Hyperscalers committed more than $350 billion in 2025 and approximately $400 billion in 2026. Every dollar of that capital faces a single bottleneck: grid connection.

The financial pressure is most acute in PJM Interconnection, the grid operator covering 13 states plus the District of Columbia. The December 2025 PJM capacity auction, for the 2027/28 delivery year, cleared at the FERC-approved price cap of $333.44/MW-day, generating $16.4 billion in total capacity costs. Data centers drove $6.5 billion of that, 40% of the total, and the auction still fell 6,623 MW short of PJM's reliability requirement.¹⁰ For context: the 2024/25 auction cleared at $28.92/MW-day. Clearing prices rose more than tenfold in a single year. The line between "data center power demand" and "everyone's utility bill" is direct and quantifiable.

Bar chart showing PJM capacity auction clearing price jumping from $28.92 per megawatt-day in 2024/25 to $333.44 per megawatt-day in 2027/28 — an 11.5-fold increase in a single year. A callout box shows the 2027/28 total capacity cost of $16.4 billion, with $6.5 billion attributable to data centers.
PJM capacity prices rose more than tenfold in 12 months. Data centers drove $6.5 billion — 40% — of the $16.4 billion 2027/28 auction total. Source: PJM Interconnection, 2027/2028 BRA Report, December 2025.

The cost allocation dispute sits at the center of RM26-4. A UCS analysis found that of 130 large load interconnection projects in PJM, only 6 (5%) required the requesting customer to pay their own connection costs directly.⁸ The remaining 95%, representing more than $4 billion in annual grid upgrade costs, were socialized across all ratepayers. The 100% participant funding model proposed under RM26-4 would transfer that burden from households to operators. GridLab calculates that if just 10% of PJM's queued projects had connected in time for the 2026/27 auction, clearing prices would have fallen to $254/MW-day, a $3.5 billion reduction.¹⁹ The system cost of the interconnection bottleneck is not theoretical. It is showing up on utility bills now.

The queue is not the only signal: 56 GW is already building its own power plants

Before examining what FERC just decided, consider what the market decided first. Cleanview identified 46 planned U.S. data centers representing 56 GW of combined behind-the-meter (BTM) capacity, approximately 30% of all tracked planned U.S. data center capacity.²⁰ Ninety percent of those projects were announced in 2025. Nearly 75% are powered by natural gas.

The BTM economics are structural, not speculative. On a 20-year levelized basis, a combined-cycle natural gas BTM solution costs $2.9 billion per 1 GW facility versus $6.2 billion for a solar-plus-storage grid-connected alternative, more than twice as expensive.²¹ The interconnection cost alone drives much of that gap: $24/kW for gas BTM versus $253/kW for solar and $335/kW for offshore wind.²¹ When grid connection costs more and takes longer than building your own plant, developers build their own plants. That is not irrational behavior. It is rational capital allocation responding to a broken process. As we documented in our analysis of data centers building their own power plants, the BTM economics were compelling before RM26-4 was filed — the June 18 show-cause orders determine how much further the gap widens.

Two-panel horizontal bar chart. Panel 1 compares 20-year levelized cost per 1 GW facility: BTM natural gas at $2.9 billion versus solar plus storage grid-connected at $6.2 billion, a 2.1-times cost difference. Panel 2 compares interconnection cost per kilowatt: gas BTM at $24, solar grid-connected at $253, and offshore wind at $335. Deployment timelines shown: BTM gas 18 to 36 months versus grid-connected 5-plus years.
When grid connection costs 10.5 times more per kilowatt and takes three to four times longer than building your own plant, developers build their own plants. That is rational capital allocation. Source: S&P Global Market Intelligence, March 2026.

The committed capital behind BTM tells the story: Williams Companies has committed $5.1 billion to data center gas-power infrastructure; VoltaGrid, Energy Transfer, and Oracle have committed 2.3 GW of off-grid gas power; Brookfield and Bloom Energy have committed up to $5 billion to solid-oxide fuel cells for data center BTM; Wärtsilä has more than 2.4 GW of U.S. data center BTM orders for 2025-2026.²⁰ Midstream capital expenditure was up 61% in 2025 and is projected up 23% in 2026. This capital is not contingent on FERC's ruling. It is already deployed.

Three-panel stat card showing: 56 GW of planned behind-the-meter data center capacity across 46 facilities; 30 percent share of all tracked planned U.S. data center capacity going behind-the-meter; and 75 percent of BTM projects powered by natural gas. A progress bar section shows committed capital from Williams Companies ($5.1B), Brookfield and Bloom Energy ($5B), VoltaGrid and Energy Transfer (2.3 GW), and Wärtsilä (2.4 GW).
The BTM defection is structural, not speculative. Ninety percent of these projects were announced in 2025. Midstream capex was up 61% that year. This capital is deployed — not contingent on FERC's June ruling. Source: Cleanview, "Bypassing the Grid," 2026.

The SPP HILL framework: proof the fast-track works

The critical piece of context for evaluating the June 18 orders is that a fast-track interconnection pathway already exists and is already operational. FERC unanimously approved the Southwest Power Pool (SPP) High Impact Large Load (HILL) framework on January 14, 2026.¹⁵ SPP's HILL process delivers interconnection agreements within 90 days for qualifying loads, cutting the national five-year average to a project-finance-compatible timeline.

The technical requirements for HILL participation define what "flexible" means in practice: hourly load forecast data provided in real time to SPP; remote disconnect capability (the grid operator, not the data center, initiates curtailment); ramp rate limits not to exceed 20 MW per minute; and full compliance with ride-through requirements, meaning the load stays connected through brief voltage and frequency deviations rather than auto-disconnecting.¹⁵ The companion HILLGA process pairs on-site generation with a HILL, delivering interconnection in 150 days with double security deposits, up to $500,000 for requests over 500 MW, and a five-year agreement after which the generator must enter the standard process.

SPP's HILL framework proves 90-day study timelines are achievable. The June 18 show-cause orders push this concept to all six RTOs, directing each to justify its current process or file a comparable fast-track threshold for loads that commit to these technical requirements.

The instrument FERC chose: a 60-day clock, not a two-year rulebook

Markets spent months handicapping two instruments. A Notice of Proposed Rulemaking (NOPR) would have proposed binding national rule text, opened a comment period, and produced an enforceable Final Rule in 12 to 24 months. A policy statement would have set interpretive principles with no binding timeline, leaving each ISO to move at its own pace. FERC chose neither. It issued tailored show-cause orders under Section 206 of the Federal Power Act to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO, plus their transmission owners, each in a docket of its own.³²

The mechanism matters because it inverts the burden of proof. Under Section 206, FERC does not propose a rule and ask whether the industry agrees. It declares the existing tariffs presumptively unjust for large loads and orders each operator to defend them or replace them within 60 days, by August 17, 2026. A resource-adequacy report, detailing how each operator will secure generation to serve new large loads, is due in 30 days.³³ Commission staff reviewed more than 3,500 pages of comments before acting. The result is faster than a NOPR and carries more compulsion than a policy statement.

Each order tees up the same five categories of reform:³³

  • Efficient study and transmission-service processes, including alternative transmission technologies

  • Preventing cost shifting and requiring transparency into transmission costs

  • Accommodating co-location and behind-the-meter generation

  • Providing new transmission services for flexible large loads

  • A process to study generation serving co-located and electrically proximate loads

Two design choices define the investment consequence. First, FERC held the jurisdictional line exactly where the market expected: the orders guard against cost shifting among transmission customers but leave retail cost allocation, generation siting, and permitting to the states, and they explicitly protect large-load transmission agreements already nearing completion.³³ Second, by tailoring orders to each operator instead of imposing one national rule, FERC preserved the regional divergence that drives the behind-the-meter trend, while pushing every operator toward faster, cost-transparent grid connection.

That combination is why this is not a binary. The five categories advance the grid-connected fast-track and entrench the behind-the-meter economics at once. The framework below maps both pathways, because after June 18 the question is no longer which outcome to position for. It is how fast you can position for both.

The full analysis continues below for paid subscribers, including detailed economic analysis, competitive landscape assessment, regulatory implications, and strategic recommendations with comprehensive citations.

Pathway 1: The grid-connected fast-track, now on the clock

User's avatar

Continue reading this post for free, courtesy of Christopher Johnson.

Or purchase a paid subscription.
© 2026 Christopher Johnson · Privacy ∙ Terms ∙ Collection notice
Start your SubstackGet the app
Substack is the home for great culture